NEWS: Kurmuk advances grid stabilisation work as December gold sales approach
NEWS: Sanku’s $4 million Ethiopian premix factory sets December opening date
NEWS: EEA report flags $1.4 billion April backlog in bank foreign exchange
NEWS: Dodai closes $16 million funding round as Tokyo Gas joins
NEWS: Metehara targets 94% rise in sugar output after disrupted season
NEWS: Ethiopia sets 12-month initial limit for financial sandbox trials
NEWS: OVID targets 20% emissions cut across construction and real estate
NEWS: Awash Insurance profit rises 65% to Br1.84 billion before tax
NEWS: Bayer plans Ethiopian wheat trials as fertiliser subsidy reaches Br100 billion
NEWS: Ethiopia’s central bank joins Islamic climate finance alliance ahead of COP32
News - Transport

ERC Targets Two-Year Completion of $1.7bn Awash–Kombolcha Railway

Oct 19, 2026
ERC Targets Two-Year Completion of $1.7bn Awash–Kombolcha Railway


  • 392 km — Ethiopian Railway Corporation (ERC) targets completion of the Awash–Kombolcha–Woldiya–Hara Gebeya railway within two years.

  • USD 1.7bn — Original railway construction contract awarded to Turkish contractor Yapı Merkezi in August 2015.

  • September 23, 2026 — Four-year arbitration dispute between ERC and Yapı Merkezi concluded in London.

  • USD 213.7m — ERC reports damages awarded to Yapı Merkezi, plus USD 29.1m in advance payments.

  • USD 307m — Yapı Merkezi separately reported its compensation award; ERC attributed the discrepancy to interest calculations.

  • Construction and repairs — ERC reports ongoing work in Kombolcha and Dessie, including conflict- and earthquake-damaged infrastructure.

  • Financing arrangements — ERC says remaining construction is budgeted but has not disclosed the amount or selected contractor.

Market Impact

  • Railway infrastructure: The planned two-year completion would advance a 392-kilometre railway project delayed by contractual disputes, payment problems and infrastructure damage.

  • Government financial exposure: The arbitration outcome establishes substantial compensation obligations. The tribunal also dismissed claims against the Ministry of Finance and Ministry of Transport and Logistics.

  • Construction and logistics: ERC's preparations indicate renewed implementation efforts, although the undisclosed construction budget, contractor and remaining work scope limit visibility into the completion plan.

Key Numbers

  • 392 km — Total railway length — infrastructure development scale.

  • 2 years — ERC's targeted completion period — construction timetable.

  • USD 1.7bn — Original construction contract — project investment value.

  • USD 213.7m — Damages reported by ERC, including interest — arbitration liability.

  • USD 29.1m — Advance payments reported separately — additional payment obligation.

  • USD 307m — Compensation reported by Yapı Merkezi — differing arbitration valuation.

  • USD 1bn+ — Contractor's original compensation demand — initial claim exposure.

  • USD 400m — Ethiopia's counterclaim — arbitration dispute scale.

  • 28 days — Appeal period following the arbitration decision — remaining legal window.

Business Signal

ERC's two-year completion target signals renewed efforts to finish the Awash–Kombolcha railway following arbitration, with construction execution and financial settlement remaining central to the project's progress.