NEWS: Kurmuk advances grid stabilisation work as December gold sales approach
NEWS: Sanku’s $4 million Ethiopian premix factory sets December opening date
NEWS: EEA report flags $1.4 billion April backlog in bank foreign exchange
NEWS: Dodai closes $16 million funding round as Tokyo Gas joins
NEWS: Metehara targets 94% rise in sugar output after disrupted season
NEWS: Ethiopia sets 12-month initial limit for financial sandbox trials
NEWS: OVID targets 20% emissions cut across construction and real estate
NEWS: Awash Insurance profit rises 65% to Br1.84 billion before tax
NEWS: Bayer plans Ethiopian wheat trials as fertiliser subsidy reaches Br100 billion
NEWS: Ethiopia’s central bank joins Islamic climate finance alliance ahead of COP32
Construction & Mining

Bishoftu International Airport Project Workforce Projections

Mar 08, 2026
Bishoftu International Airport Project Workforce Projections
  • Bishoftu International Airport construction workforce projected 50,000 workers in 2026, according to project labor demand estimates.

  • Workforce expected 70,000 in 2027, 90,000 in 2028, and 100,000 in 2029 during peak construction period.

  • Labor management plan prepared by Dar Al-Handasah Consultants and Ethiopian Engineering Corporation.

  • Airport project led by Ethiopian Airlines Group to expand national aviation capacity.

  • Airport planned in Bishoftu, 40 km southeast of Addis Ababa.

  • Project designed to supplement operations at Addis Ababa Bole International Airport.

why it matters?
The project will employ tens of thousands during construction and expand Ethiopia’s aviation infrastructure. Increased capacity may support aviation, logistics, and related services sectors.